MDG is providing civil engineering design services for this project, which primarily comprises constructing a new ramp and blast deflector fence for an FBO facility. The new ramp requires demolishing an existing building, parking lots, and ramp pavements and installing a new concrete pavement ramp designed to accommodate aircraft such as Antonovs, B-757s, B-747s, and A-340s. The concrete from the existing ramp will be recycled and incorporated into the new ramp. The ramp is approximately 450,000 SF. A new taxilane (ADG II, TDG 2) will also be constructed to improve maneuverability and provide a new aircraft taxiing route to increase parking capacity on the existing ramp.
Other project components include installing blast deflectors and new AOA fencing, replacing an existing Oil/Water Separator (OWS), and constructing an additional +/- 2,000 SF asphalt paved equipment parking area.